Vice Chairman of Long An People's Committee - Pham Tan Hoa surveys construction progress of Thien Ho Duong High School

On September 15, Vice Chairman of Long An People's Committee - Pham Tan Hoa and some provincial departments and branches came to survey the construction progress of Thien Ho Duong High School in Kien Tuong town.

Vice Chairman of Long An People's Committee - Pham Tan Hoa suggests the construction unit to speed up the progress, but ensure the technique, work quality and labor safety

Vice Chairman of Long An People's Committee - Pham Tan Hoa suggests the construction unit to speed up the progress, but ensure the technique, work quality and labor safety

Thien Ho Duong High School sponsored by the former State President - Truong Tan Sang was started construction on October 28, 2019. The school has 22 classrooms, 12 functional rooms, archives, libraries, 4 blocks of classrooms, multi-functional rooms and ancillary works. Total investment cost is over 130 billion VND.

According to the report of the construction unit, the work has been done 65 percent of the quantity up to now. However, the rainy weather and the effects of the Covid-19 epidemic had been delayed. The contractor is concentrating on labor to complete main items such as classrooms, building blocks, multi-functional houses, etc.

Thien Ho Duong High School project has done 65 percent of the work up to now

 Thien Ho Duong High School project has done 65 percent of the work up to now

At the meeting, the construction unit, the investor, the supervision consultant unit agreed on October 27, 2020 to complete the classrooms and building blocks, the main school yard, equipment installation and ensure the conditions to welcome students to school. Particularly, items such as fences, football fields, swimming pools and auxiliary works are basically completed by the end of December.

Vice Chairman of the Provincial People's Committee - Pham Tan Hoa emphasized that this was the first high-quality school in the area, with a full range of classrooms, laboratories, offices, auxiliary areas according to national standards. It will help the teaching and learning in the area better, contributing to the training of high human resources in the future. Therefore, relevant units need to coordinate to remove difficulties, problems, speed up construction progress, but ensure technical and quality factors for the works to be accepted and put into use soon as planned./.

By Tuan Hung – Translated by Duc Tam