Duc Hoa 3 110-kilovolt substation put into operation

On December 20, Long An Power Corporation (PCLA) decided to put into operation the Duc Hoa 3 110-kilovolt substation.

The Duc Hoa 3 110-kilovolt substation which has a capacity of 2x63MVA was built by Vietnam Electricity Southern Power Corporation (EVNSPC) with an investment cost of over 100 billion VND. The work is located on Street No.1, Xuyen A Industrial Zone, My Hanh Bac Commune, Duc Hoa District.

The Duc Hoa 3 110-kilovolt substation is put into operation

The Duc Hoa 3 110-kilovolt substation is put into operation

The Duc Hoa 3 110-kilovolt substation was accomplished to ensure the stability and sufficiency in electricity supply to satisfy the demand of enterprises' production and business as well as the daily needs of people in the area. On the other hand, it also changes the operating electrical grid to optimize 22kV substations, ensures the voltage quality and reduces the loss of electrical energy.

Now, EVNSPC assigns PCLA to exploit, run and manage to ensure the efficient development of the Duc Hoa 3 110-kilovolt substation as the proposed plan./.

By Luc Nguyen – Translated by Duc Tam

Sourcehttps://baolongan.vn/dua-vao-van-hanh-tram-bien-ap-110kv-duc-hoa-3-a107195.html