Long An: 2019 is breakthrough year in compensation, site clearance and resettlement

Secretary of Party Committee, Chairman of People's Council of Long An Province - Pham Van Ranh directed that 2019 was a breakthrough year in compensation, site clearance and resettlement at the symposium on this issue held by the Provincial Party Committee on March 8. Vice Chairman of the Provincial People's Committee - Nguyen Van Duoc and leaders of departments, sectors, districts and cities in the province attended the symposium.

Many opinions and reports were presented at the symposium by leaders of sectors and localities on problems in implementing the compensation, site clearance and resettlement such as compensation prices, lateness in compensation, many projects compensated in a long time, investors not implementing projects, etc. Many opinions focused on analyzing and evaluating, clarifying the causes and limitation on the responsibilities of the sectors and localities in performing their tasks.

Secretary of Provincial Party Committee - Pham Van Ranh emphasized that the compensation, site clearance and resettlement in the province have not met the requirements over the past time yet. The results and progress of dealing with ground clearance were still done slowly and long-lasting by some sectors and units.

Secretary of Provincial Party Committee, Chairman of Provincial People's Council - Pham Van Ranh assessed that compensation, site clearance and resettlement have not met the requirements.

Secretary of Provincial Party Committee, Chairman of Provincial People's Council - Pham Van Ranh assessed that compensation, site clearance and resettlement have not met the requirements yet.

At this symposium, Secretary of Provincial Party Committee requested that units, localities and executive committees of the party hierarchy frankly recognized the limitations. Since then, solutions have been implemented and corrected to create a transformation in the coming time. 2019 will be a breakthrough year in compensation, site clearance and resettlement.

He asked the provincial People's Committee to assign and specify tasks and direct drastically for each department, sector and locality in the implementation of compensation, site clearance and resettlement. The key projects need to clearly identify requirements and set the time for implementation. Projects must be transparent about planning, implementation schedule and progress so that people can monitor to avoid long-lasting price appraisal and distraint.

Besides, the whole political system must take part in propaganda on compensation, site clearance, resettlement which creates smooth understanding and consensus to implement the project. To continue strengthening and consolidating the Land Clearance Board and the force of distraining and applying land compensation prices to meet the task requirements, it must be professional, objective and honest in performing tasks. The participants must have proper roles when conducting to determine and appraise compensation prices for land clearance.

In addition, the Secretary of the Provincial Party Committee also noted that we must regularly review investors implementing projects; If the project is carried out slowly, deliberately, long-lasting and causing pressing, a solution must have been done. Real estate is paid attention and directed, controlled and handled violations strictly. The Secretary and Chairman of People's Committees at district and commune level must well meet and talk dialogue with the people. Through these, the legitimate requirements of the people must be resolved quickly and promptly.

Monitoring the progress of implementing some projects in Ben Luc district in 2018

Monitoring the progress of implementing some projects in Ben Luc district in 2018

“It is necessary to resolve and implement well the security and order in the projects. Acts of inciting security and order in the project areas or hindering the implementation of the project are strictly dealed with. On the side of the press agencies in the province, the propaganda on projects must be strengthened, transparent and it is necessary to inform and reflect projects that are late, prolonged so that  the provincial leaders timely grasp and instruct to solve and rectify", the Secretary of Provincial Party Committee - Pham Van Ranh directed.

Secretary of the Provincial Party Committee - Pham Van Ranh emphasizes that this is a very important conference and reiterates the requirement that departments, sectors and localities must have solutions to overcome the above problems and limitations over the past time. 2019 will be a breakthrough year for this issue./.

By Le Duc – Translated by Duc Tam

According to the report of the Provincial People's Committee, there were 98 projects implemented in 2018, the total area of land acquisition was nearly 349 hectares, nearly 6,800 affected households, the total amount payment  of compensation and support over VND 1,571 billion.

Source: http://baolongan.vn/bi-thu-tinh-uy-long-an-2019-la-nam-dot-pha-ve-cong-tac-boi-thuong-giai-phong-mat-bang-tai-dinh-cu-a71914.html