Chairman of Provincial People's Committee - Nguyen Van Ut inspects key traffic projects in Duc Hoa district

On June 5, a working delegation led by Deputy Secretary of Provincial Party Committee, Chairman of Provincial People's Committee - Nguyen Van Ut inspected the progress of key traffic projects in Duc Hoa district, Long An province. Accordingly, the delegation surveyed the progress of Provincial Road 823D and 822B.

Chairman of the Provincial People's Committee - Nguyen Van Ut inspects the progress of key traffic projects in Duc Hoa

The Provincial Road 823D project has a length of 14.2km, the starting point intersects with the newly opened Northwest road at Ranh canal, the ending point is at the intersection of National Highway N2 with Ho Chi Minh Road. The project is invested with a road surface of 4 lanes of 14m wide, 2 parallel lanes of 7m wide, roadbed of 32m - 40m wide. Total investment is nearly 1,106 billion VND, in which central budget supports of 1,000 billion VND, the rest is provincial budget capital and other legally mobilized sources. Currently, contractors are deploying 6 construction projects. Realized volume value is at 43.02%.

However, during site clearance work, the Tua 1 intersection in Duc Hoa town still has 12 households stuck. The contractor requests to consider adjusting the price for the contract advance to the price notice of the Department of Construction.

Provincial Road 822B project (the section from Provincial Road 825 connecting Provincial Road 838 with Ho Chi Minh Road) has a length of about 11.4km; Investment in phase 1 of level IV plain road includes 7m wide asphalt surface, 9m wide road base. Vam Co Dong bridge section has load capacity of HL93. Total investment is more than 918 billion VND. The scope of site clearance for the completion phase is 30m wide. Vam Co Dong bridge is constructed by Hop Thanh - North Central South Joint Venture, from May 4, 2023 - June 3, 2025. The value of the implemented volume reached 30%.

Through actual inspection and listening to reports from the local side and Department of Transport, Chairman of Provincial People's Committee - Nguyen Van Ut emphasized that provincial departments and branches need to coordinate closely with localities and implementation units to speed up construction progress and complete site clearance work early; focus on removing difficulties and accelerating the progress of projects.

Particularly for the Provincial Road 823D project, Chairman of Provincial People's Committee requested that Duc Hoa district drastically focus on leading and directing the completion of clean site clearance work for the entire route in June. At the same time, he assigned the Department of Transport and The Project Management Board to work with the construction unit to mobilize maximum resources to construct the area that has been handed over, ensuring progress, quality, and the proposed plan.

During the implementation process, if there are any problems, he recommended to specifically report to Provincial People's Committee for timely removal and resolution./.

By Staffs - Translated by Q. Thien