Provincial Road 830E must be completed before 2026

Deputy Secretary of the Provincial Party Committee and Chairman of the Tay Ninh Provincial People’s Committee Nguyen Van Ut requested the immediate removal of obstacles to accelerate the project’s progress, stressing that the road must be inaugurated and implemented by 2026 to serve socio-economic development.

On September 11, Deputy Secretary of the Provincial Party Committee and Chairman of the Tay Ninh Provincial People’s Committee Nguyen Van Ut, together with a working delegation, inspected the progress and site clearance of the Provincial Road 830E project. Joining the delegation were members of the Provincial Party Standing Committee, Vice Chairman of the Provincial People’s Committee Nguyen Minh Lam, leaders of provincial departments and sectors, and representatives of the relevant commune People’s Committees.

Delegates attending the meeting

The Provincial Road 830E project spans over 9.3km, starting at the Ben Luc interchange of the Ho Chi Minh City–Trung Luong Expressway in Ben Luc Commune and ending at Provincial Road 830 in Long Cang Commune, Tay Ninh Province. Phase 1 includes the construction of two parallel roads along the route, each comprising two 7m-wide mixed-traffic lanes and one 2.5m-wide lane for rudimentary vehicles, as well as bridges crossing rivers on both sides

The connecting section to Provincial Road 830 is designed with 6 lanes, a 20m carriageway, and a 30m roadbed. In its completed phase, the project will become an expressway with 8 running lanes and 2 emergency lanes, while the parallel roads will feature 4 mixed-traffic lanes, 2 lanes in each direction.

Deputy Director of Long An Construction Investment Project Management Board, Tran Thien Truc, informs about the project implementation progress

The province is focusing on implementing the 5.8km section of the project from the Provincial Road 830 interchange to National Highway 1, passing through Ben Luc and My Yen communes. For site clearance, compensation has been paid to 798/878 cases, with a total amount of 1,456 billion VND, reaching 89% in cases and 91.6% in area. 80 households have not yet received compensation.

For construction progress on the section from the Provincial Road 830 interchange to National Highway 1, all 4 construction packages executed by contractors have achieved between 37–51%. The biggest challenge lies in site clearance, as some households have not agreed to hand over land, affecting construction progress.

Deputy Secretary of the Provincial Party Committee and Chairman of the Tay Ninh Provincial People’s Committee Nguyen Van Ut and the working delegation inspect the project site

At the meeting, leaders of provincial departments and sectors proposed solutions to remove obstacles and accelerate project progress.

Member of the Provincial Party Standing Committee and Vice Chairman of the Provincial People’s Committee Nguyen Minh Lam requested Ben Luc and My Yen commune authorities to intensify communication and persuasion efforts to encourage residents to promptly hand over land. For households that have received compensation but not yet handed over land, local authorities should persuade them to implement temporary relocation policies.

For those refusing compensation, dossiers must be consolidated and procedures followed properly to enforce land recovery, ensuring timely site clearance and handover to contractors to accelerate project progress.

Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee Nguyen Van Ut, speaks at the meeting

Speaking at the meeting, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People’s Committee Nguyen Van Ut requested provincial departments, sectors, and local authorities to make the utmost effort to promptly remove difficulties and obstacles, so that the road can be inaugurated and put into operation no later than 2026, serving socio-economic development.

He also asked the Long An Construction Investment Project Management Board to coordinate with the Department of Finance and the Provincial People’s Committee Office to advise on project scale adjustment and investment capital sources, to be submitted at the upcoming session of the Provincial People’s Council.

In addition, Chairman Nguyen Van Ut requested the Project Management Board to work with the Department of Construction to advise the Provincial People’s Committee on establishing the Ho Chi Minh City Ring Road 4 Project Management Board./.

By Staff – Translated by Tuong Vinh

Source: https://baolongan.vn/cham-nhat-nam-2026-phai-hoan-thanh-duong-tinh-830e-a202320.html